Abstract:
Objective The mutual constraints among the overall layout, structural design, and float-over installation of large offshore converter stations require an integrated design method that considers them comprehensively.
Method Based on CGN's 2000 MW offshore wind farm project in Jieshi Bay, Shanwei, Guangdong, the platform functional layout, topside weight and center of gravity, jacket opening and platform elevation, number and type of main legs, LMU/DSU capacity, and installation vessel type were incorporated into a unified design. The jacket opening, platform elevation and leg layout were back-calculated from the float-over installation conditions. Staged analyses were carried out for load-out ballasting, transport stability, vessel entry positioning, load transfer, and vessel retreat clearance requirements.
Result The float-over clearance requirement becomes the governing condition for the platform bottom elevation. The jacket opening is taken as 48 m, and the number of main legs is 12. The "HYSY 229" barge is selected, and the longitudinal entry direction is adopted. The load-out stability, transport stability, vessel entry positioning, and vessel retreat clearance generally meet the requirements.
Conclusion The integrated design method that comprehensively considers the overall layout, structure, and float-over installation can provide a reference for the overall scheme design, float-over installation method, and construction scheme of large offshore converter stations.