基于多尾流模型的大型海上风电场扩容试验研究

蔡彦枫 徐初琪 汤东升 王晴勤

蔡彦枫, 徐初琪, 汤东升, 王晴勤. 基于多尾流模型的大型海上风电场扩容试验研究[J]. 南方能源建设, 2023, 10(4): 138-147. doi: 10.16516/j.gedi.issn2095-8676.2023.04.014
引用本文: 蔡彦枫, 徐初琪, 汤东升, 王晴勤. 基于多尾流模型的大型海上风电场扩容试验研究[J]. 南方能源建设, 2023, 10(4): 138-147. doi: 10.16516/j.gedi.issn2095-8676.2023.04.014
CAI Yanfeng, XU Chuqi, TANG Dongsheng, WANG Qingqin. Experimental Research on Capacity Expansion of Large-Scale Offshore Wind Farm Under Multiple Wake Models[J]. SOUTHERN ENERGY CONSTRUCTION, 2023, 10(4): 138-147. doi: 10.16516/j.gedi.issn2095-8676.2023.04.014
Citation: CAI Yanfeng, XU Chuqi, TANG Dongsheng, WANG Qingqin. Experimental Research on Capacity Expansion of Large-Scale Offshore Wind Farm Under Multiple Wake Models[J]. SOUTHERN ENERGY CONSTRUCTION, 2023, 10(4): 138-147. doi: 10.16516/j.gedi.issn2095-8676.2023.04.014

基于多尾流模型的大型海上风电场扩容试验研究

doi: 10.16516/j.gedi.issn2095-8676.2023.04.014
基金项目: 中国能建广东院科技项目“大规模海上风电场细分场址及容量控制指标研究”(EV06731W);中国电力工程顾问集团有限公司科技项目“广东省海上风电海洋水文气象信息预报关键技术研究”(GSKJ2-W01-2021)
详细信息
    作者简介:

    蔡彦枫,1986-,男,高级工程师,南京大学大气物理学与大气环境硕士,主要从事海上风资源评估、台风影响论证及微观选址技术研究工作(e-mail)caiyanfeng@gedi.com.cn

    徐初琪,1976-,男,高级工程师,大学本科,主要从事海洋钢材腐蚀评估及防护工作(e-mail)

    汤东升,1961-,男,正高级工程师,主要从事海上风电项目技术研究和审核工作(e-mail)tangdongsheng@gedi.com.cn

    王晴勤,1982-,男,高级工程师,华南理工大学工学硕士,主要从事海上风电规划与总体设计工作(e-mail)wangqingqin@gedi.com.cn

    通讯作者:

    蔡彦枫,1986-,男,高级工程师,南京大学大气物理学与大气环境硕士,主要从事海上风资源评估、台风影响论证及微观选址技术研究工作(e-mail)caiyanfeng@gedi.com.cn

  • 中图分类号: TK89;TM614

Experimental Research on Capacity Expansion of Large-Scale Offshore Wind Farm Under Multiple Wake Models

图(5) / 表 (3)
计量
  • 文章访问数:  145
  • HTML全文浏览量:  26
  • PDF下载量:  64
  • 被引次数: 0
出版历程
  • 收稿日期:  2023-01-03
  • 修回日期:  2023-03-15
  • 网络出版日期:  2023-07-25
  • 刊出日期:  2023-07-10

基于多尾流模型的大型海上风电场扩容试验研究

doi: 10.16516/j.gedi.issn2095-8676.2023.04.014
    基金项目:  中国能建广东院科技项目“大规模海上风电场细分场址及容量控制指标研究”(EV06731W);中国电力工程顾问集团有限公司科技项目“广东省海上风电海洋水文气象信息预报关键技术研究”(GSKJ2-W01-2021)
    作者简介:

    蔡彦枫,1986-,男,高级工程师,南京大学大气物理学与大气环境硕士,主要从事海上风资源评估、台风影响论证及微观选址技术研究工作(e-mail)caiyanfeng@gedi.com.cn

    徐初琪,1976-,男,高级工程师,大学本科,主要从事海洋钢材腐蚀评估及防护工作(e-mail)

    汤东升,1961-,男,正高级工程师,主要从事海上风电项目技术研究和审核工作(e-mail)tangdongsheng@gedi.com.cn

    王晴勤,1982-,男,高级工程师,华南理工大学工学硕士,主要从事海上风电规划与总体设计工作(e-mail)wangqingqin@gedi.com.cn

    通讯作者: 蔡彦枫,1986-,男,高级工程师,南京大学大气物理学与大气环境硕士,主要从事海上风资源评估、台风影响论证及微观选址技术研究工作(e-mail)caiyanfeng@gedi.com.cn
  • 中图分类号: TK89;TM614

摘要:   目的  文章旨在研究大型海上风电场的最佳规划容量设置。  方法  针对某1 GW容量的单个规划场址,利用3种不同单机容量机型与3种海上风电场尾流模型,结合海上风资源图谱开展同场址逐步扩容至2 GW的一系列数值试验,并对全场发电量、尾流影响与边际效应进行分析。  结果  结果显示,随着机型的单机容量增大,扩容过程中全场实际发电量增幅越高,尾流损失增长越慢,兼顾机组安全性与投入产出比的有效扩容区间越大;但尾流模型选择可能影响有效扩容区间评估结果。  结论  文章研究表明,在满足现有用海指标、风电机组安全性与工程经济性等多重约束下,单个场址的最佳规划容量可以略高于现有基准值,在今后海上风电千万千瓦级基地规划中,应科学细分并合理设置单个场址的规划容量。

English Abstract

蔡彦枫, 徐初琪, 汤东升, 王晴勤. 基于多尾流模型的大型海上风电场扩容试验研究[J]. 南方能源建设, 2023, 10(4): 138-147. doi: 10.16516/j.gedi.issn2095-8676.2023.04.014
引用本文: 蔡彦枫, 徐初琪, 汤东升, 王晴勤. 基于多尾流模型的大型海上风电场扩容试验研究[J]. 南方能源建设, 2023, 10(4): 138-147. doi: 10.16516/j.gedi.issn2095-8676.2023.04.014
CAI Yanfeng, XU Chuqi, TANG Dongsheng, WANG Qingqin. Experimental Research on Capacity Expansion of Large-Scale Offshore Wind Farm Under Multiple Wake Models[J]. SOUTHERN ENERGY CONSTRUCTION, 2023, 10(4): 138-147. doi: 10.16516/j.gedi.issn2095-8676.2023.04.014
Citation: CAI Yanfeng, XU Chuqi, TANG Dongsheng, WANG Qingqin. Experimental Research on Capacity Expansion of Large-Scale Offshore Wind Farm Under Multiple Wake Models[J]. SOUTHERN ENERGY CONSTRUCTION, 2023, 10(4): 138-147. doi: 10.16516/j.gedi.issn2095-8676.2023.04.014
    • 在“碳达峰、碳中和”战略目标指引下,国内海上风电迎来了新一轮发展机遇。国家《“十四五”可再生能源发展规划》中明确提出,推动山东半岛、长三角、闽南、粤东、北部湾等千万千瓦级海上风电基地开发建设,推动一批百万千瓦级的重点项目集中连片开发。广东、广西、海南等地的省级海上风电规划中,深水区单个场址的规划容量都在百万千瓦甚至更高。可以预见,今后海上风电发展将呈现大容量、集中连片和深远海等新特点[1-3]

      随着海上风电场规模的扩大与离岸距离的增加,海上风电场的确权用海面积和风电场外缘边线包络海域面积同步增大,给自然资源主管部门在海上风电用海审批与管理上带来了新挑战[4]。2016年,原国家海洋局出台了国海规范〔2016〕6号文件,基于当时5~6 MW级别机组与浅水区场址提出了“单个海上风电场外缘边线包络海域面积原则上每100 MW控制在16 km2左右”这一指标。现阶段深远海风电机组的单机容量和单个风电场规划容量均已大幅提高,上述用海指标能否继续适用值得讨论。因此,有必要进行大型海上风电场址规划容量设置研究,探讨已有场址扩容的可行性,并进一步揭示最大限度集约节约用海、风电机组安全性与工程经济性等多重约束下的最佳规划容量范围。

      目前,国内关于海上风电场规划容量设置的研究相对较少,所采用的方法主要为考虑风能资源、建设成本、运营方式、电网消纳等方面的约束条件[5-7],构建多目标决策函数,求解优化问题的最优解[8-10]。但已有研究中的机组单机容量和规划面积均偏小,风电机组之间的尾流效应考虑得较为简单,与吉瓦级别的大型海上风电场实际情况存在差异。为此,本文以某大型海上风电规划场址为研究对象,利用10 MW级别以上的典型机型,结合风资源图谱、海上风电场尾流模型对同一场址逐步扩容情景下的发电效率、尾流损失与边际效应分析,并对今后大型海上风电场规划容量设置与风电基地场址细分工作提出建议。

    • 图1所示,本文研究对象为某规划场址群中的单个1 GW细分场址,离岸约60 km;场址形状为矩形,东西方向长约23.2 km,南北方向长约6.9 km,面积为160 km2

      图  1  研究场址与风资源数据示意图

      Figure 1.  Schematic diagram of wind farm site under research and wind resource atlas

      由于场址覆盖范围较大,场内不同机位处的风资源存在空间分布差异,因此以往研究中用单个测风塔的风资源数据代表所有机位来计算全场发电量的做法存在缺陷。本文利用能够反映风资源实际空间分布差异的数据集——全球风能图谱(Global Wind Atlas, GWA)[11]作为风资源输入资料。GWA是丹麦理工大学与世界银行合作开发的全球250 m分辨率风资源数据库,提供全球陆地与距离海岸线200 km以内海面上10 m、50 m、100 m、150 m、200 m共5个高度层的风资源参数。本文采用GWA网站(https://globalwindatlas.info/)公开发布的v3.2版本数据,下载位于场址内,间隔3 km共计16个数据格点的风况参数(Weibull分布参数和每30°扇区的风向频率)进行后续的发电量计算,其中150 m高度的平均风速空间分布如图1所示。

    • 表1所示,本文选用设计等级相同,单位千瓦扫风面积相近且适合研究海域风资源条件的3种10 MW以上风电机组,进行后续1 GW基准容量逐步扩容至2 GW的机组排布与对比。

      表 1  对比机型概况

      Table 1.  Wind turbines information

      机型WTG1WTG2WTG3
      单机容量/MW111216
      设计等级IEC SIEC SIEC S
      叶轮直径/m208220256
      轮毂高度/m130140150

      其中,WTG1机型共设10个规划容量情景,对应装机数目依次为90、100、110、121、132、143、154、165、176、187台;WTG2机型共设8个规划容量情景,装机数目依次为88、99、110、121、132、143、154、165台;WTG3机型共设8个规划容量情景,装机数目依次为63、72、81、90、99、108、117、126台。

      采用实际工程微观选址中最常用的阵列排布法[12-13],对表1所列的WTG1~WTG3机型不同规划容量情景,设计具体排布方案:根据规划台数,沿场址边界由南向北、由西向东按照近似相同的间距排布逐个机位,充分利用场址内部空间形成机组阵列,使得主导风向扇区(30°~60°)中前后机位的间距最大,降低尾流损失;并且相邻机位的最小间距控制在3DD为叶轮直径)以上,确保机组安全运行。其中,WTG1机型90台(990 MW)和187台(2.057 GW)两种规划容量情景下的布置方案对比如图2所示,其他方案图略。

      图  2  排布方案与尾流计算结果示意图

      Figure 2.  Schematic diagram of wind turbine layouts and wake calculation results

    • 相关研究表明,大型海上风电场尾流效应更为显著[14],其对发电量计算的影响不容忽视。在本文中,利用Park、Bastankhak、Fuga共3种尾流模型进行不同排布方案的尾流影响分析与对比,相关说明如下:

      1)Park模型

      Park模型(以下简称P模型)是描述平坦地形下的一维解析尾流模型[15],同样适用于海上风电情形。其原理是假定风速为U的气流经过机组叶轮被吸收一部分能量后,在整个叶轮范围内形成均匀的尾流区(风速均降为U),因此,属于一维模型。尾流区宽度随着向下风方向扩散距离而呈线性增加,风速衰减δU逐渐恢复,表达式如下:

      $$ {\delta_U}(x) = \dfrac{{{U_\infty } - U}}{{{U_\infty }}} = (1 - \sqrt {1 - {C_{\rm{t}}}} )\dfrac{D}{{D + 2kx}}\dfrac{{{A_{{\rm{overlop}}}}}}{{{A_{{\rm{wtg}}}}}} $$ (1)

      式中:

      Ct ——机组推力系数;

      D ——机组叶轮直径(m);

      k ——P模型所定义的尾流扩展系数,根据广东海域已有研究成果[16],本文中k取值为0.044;

      x ——尾流向下风方向的扩散距离(m);

      Aoverlap——速度衰减区与下游机组叶轮重叠面积(m2);

      Awtg ——下游机组叶轮面积(m2)。

      2)Bastankhak模型

      Bastankhah模型(以下简称B模型)是基于正态分布,由动量守恒及质量守恒推导得到的新一代二维解析尾流模型,相关研究表明,正态分布比P模型中的均匀分布更符合尾流区内的风速衰减形态,与实测结果相比误差更小[17-19]。速度损失δU表达式如下:

      $$ \begin{array}{l}{\delta_U}(x,y)=1-\sqrt{1-\dfrac{{C}_{{\rm{t}}}}{8(\dfrac{{k}_x^{*}}{D}+0.2\sqrt{\beta })^{2}}}\times \\ \text{exp}\left[-(y/D)^{2}/2\left( {\dfrac{{k}_x^{*}}{D}+0.2\sqrt{\beta }} \right)^{2}\right]\end{array} $$ (2)
      $$ \beta = \dfrac{{1 - \sqrt {1 - {C_{\rm{t}}}} }}{{2\sqrt {1 - {C_{\rm{t}}}} }} $$ (3)

      式中:

      y ——尾流区内沿轮毂中心向边缘扩展的距离(m);

      k* ——B模型所定义的尾流扩展系数,在本文中参考已有研究成果[19]k*取值为0.018;

      其余变量与P模型中的变量一致。

      3)Fuga模型

      Fuga模型(以下简称F模型)是一种线性化的三维计算流体力学(CFD)模型,是丹麦Risø国家实验室开发WAsP Fuga软件中的尾流计算模型,用于大型海上风电场在不同大气稳定度下的尾流效应快速计算。F模型的原理是基于平流、气压梯度力、湍流应力和机组叶轮对气流的阻力等效应下的定常不可压雷诺平均方程(RANS),并对RANS方程进行线性化和摄动展开,再利用快速傅里叶积分变换法求解线性方程的数值解[20]

      F模型的线性化方程如下:

      $$ \begin{gathered} {u^0}\dfrac{{\partial {u^1}}}{{\partial x}} + {w^1}\dfrac{{\partial {u^0}}}{{\partial z}} = - \dfrac{{\partial {p^1}}}{{\partial x}} + \\ \dfrac{\partial }{{\partial {x_j}}}{k} {u_*}z\left( {\dfrac{{\partial {u^1}}}{{\partial {x_j}}} + \dfrac{{\partial u_j^1}}{{\partial x}}} \right) + f_1^1 \\ \end{gathered} $$ (4)
      $$ {u^0}\dfrac{{\partial {v^1}}}{{\partial x}} = - \dfrac{{\partial {p^1}}}{{\partial y}} + \dfrac{\partial }{{\partial {x_j}}}{k} {u_*}z\left( {\dfrac{{\partial {v^1}}}{{\partial {x_j}}} + \dfrac{{\partial v_j^1}}{{\partial x}}} \right) $$ (5)
      $$ {u^0}\dfrac{{\partial {w^1}}}{{\partial x}} = - \dfrac{{\partial {p^1}}}{{\partial z}} + \dfrac{\partial }{{\partial {x_j}}}{k} {u_*}z\left( {\dfrac{{\partial {w^1}}}{{\partial {x_j}}} + \dfrac{{\partial w_j^1}}{{\partial x}}} \right) $$ (6)
      $$ \dfrac{{\partial {u^1}}}{{\partial x}} + \dfrac{{\partial {v^1}}}{{\partial y}} + \dfrac{{\partial {w^1}}}{{\partial z}} = 0 $$ (7)
      $$ \begin{gathered} f_1^1 = - \dfrac{1}{2}{C_{\rm{t}}}U_\infty ^2\text{δ} (x - {x_{\rm{h}}})\Theta \Bigg[{\left( {\dfrac{D}{2}} \right)^2} - \\ {(y - {y_{\rm{h}}})^2} - {(z - {z_{\rm{h}}})^2}\Bigg] \\ \end{gathered} $$ (8)

      式中:

      unvnwn——风矢量在三维笛卡尔坐标中x(顺风向)、y(横风向)、z(垂向)3个轴向上的摄动展开(m/s),n=0和1;

      p1 ——气压的一阶摄动展开(hPa);

      uj1 ——风速分量在特定方向上的一阶摄动展开(m/s),j=1、2、3,u1=uu2=vu3=w

      xj ——三维笛卡尔坐标中的三个轴向,x1=xx2=yx3=z

      δ() ——狄拉克函数;

      Θ() ——阶梯函数,负值取0,正值取1;

      xhyhzh——机组轮毂中心点坐标;

      其余变量与P模型中的变量一致。

      4)尾流叠加方式

      上述3种尾流模型中,多台机组的尾流叠加效应均采用速度衰减平方和形式:

      $$ {\delta_U} = \sqrt {\displaystyle \sum\limits_{i = 1}^n {\delta_{U_i^2}} } $$ (9)

      式中:

      ${\delta _{{U_i}}} $ ——第i台机组产生的速度衰减(m/s);

      n ——尾流叠加计算中的机组总数(台)。

    • 设置一系列数值试验,依次进行WTG1~WTG3机型全部排布方案的发电量与尾流损失计算:(1)建立排布方案中各个机位的经纬度坐标与GWA数据格点的对应关系,在风电场发电量计算软件WAsP v11.0中建立多个机组群(Turbine Stie Group)并关联各自风能图谱(Wind Atlas),导入对应的GWA数据格点文件(lib格式),再输入相应机型的功率曲线与推力系数文件(wtg格式),利用软件生成机组轮毂高度的风资源并得到P模型的试验结果(逐机位的发电量与尾流损失);(2)在WAsP软件中生成并导出轮毂高度的风能图谱文件(wrg格式),结合(1)中的wtg文件与式(2)~式(3)分别计算排布方案逐机位、逐风向扇区的发电量与尾流损失,得到B模型的试验结果;(3)将WAsP软件的计算模型文件(wwh格式)导入WAsP Fuga v2.9.6.1软件中,设置大气稳定度为中性,进一步计算得到F模型的试验结果。

    • 对同一机型在不同规划容量情景下的全场总发电量与各机位平均尾流损失进行归一化,计算式如下:

      $$ {P'_i} = {P_i}/{P_1} $$ (10)
      $$ {W'_i} = {W_i}/{W_1} $$ (11)

      式中:

      Pi ——第i个规划容量情景中的总发电量(MWh);

      P1 ——基准容量情景下的总发电量(MWh);

      Wi ——第i个规划容量情景中的平均尾流损失(%);

      W1 ——基准容量情景下的平均尾流损失(%)。

      PiWi随规划容量的变动趋势进行一元线性回归拟合:

      $$ Y = aX + c $$ (12)

      式中:

      Y ——PiWi

      X ——规划容量(MW);

      a ——斜率拟合值;

      c ——截距拟合值。

      进一步加入规划容量变动的经济性因素,设置不同规划容量情景的边际效应参数E

      $$ {E_{i{\text{,}}j}} = \dfrac{{({P_{i,j}} - {P_{1,j}})}}{{({X_{i,j}} - {X_{1,j}})}}/\dfrac{{({P_{{\text{2,WTG1}}}} - {P_{1,{\text{WTG}}1}})}}{{({X_{{\text{2,WTG1}}}} - {X_{1,{\text{WTG}}1}})}} $$ (13)

      式中:

      i ——第i个容量情景,i=1, 2, …, N

      j ——第j种机型,j为WTG1、WTG2、WTG3;

      N ——WTG1、WTG2、WTG3中特定机型规划容量情景总数。

    • 以WTG1机型为例,分析不同规划容量情景下P'W'的具体变幅。如图3所示,3种尾流模型的试验结果均显示,总发电量和平均尾流损失均随着规划容量的增加而增加,但具体增幅差异显著。按照式(12)进行整体变化趋势拟合,总发电量变化趋势拟合关系中的斜率a均小于1(3种尾流模型试验a分别为0.78、0.81、0.80);而平均尾流损失变化趋势拟合关系中的斜率均大于1(3种尾流模型试验a分别为1.45、1.43、1.71),说明尾流损失增幅要快于总发电量增幅。上述现象反映了大型海上风电尾流效应对机组出力的直接影响,即如图2所示,在一定的海域面积内,随着装机数目的增加,出现了更多尾流区的相互叠加,并且机位间距下降导致速度衰减难以充分恢复,尾流损失增大。而在风资源不变的情况下,下风向机位处的实际风速出现严重下降,导致机组难以发挥正常的做功性能,在宏观上表现为机组数目增加所带来的风能捕获增量被更为严重的尾流损失抵消,最终导致实际发电量的增幅低于装机容量增幅。对于WTG2和WTG3机型的分析结果相近。

      图  3  不同规划容量情景下的总发电量与平均尾流损失变化

      Figure 3.  Changes in total power generation and mean wake loss in different planned capacity situations

      进一步开展3种不同容量机型之间的对比,如表2所示,WTG1、WTG2和WTG3机型总发电量变化趋势的斜率a取3种尾流模型试验平均值,分别为0.797、0.803、0.833。可以发现,随着机组单机容量的增大,发电量拟合关系中a值出现小幅上升的倾向,原因在于采用更大单机容量机型,相同规划容量情景下的装机数目更少,排布方案中的机位间距更大,更有利于尾流损失的恢复与控制。因此,所得到的实际发电量增幅高于其他机型。说明在大型海上风电场容量设置中采用大容量机型,具有发电效率上的天然优势。

      表 2  不同机型的总发电量与平均尾流损失变化拟合

      Table 2.  Linear fitting of total power generation and mean wake loss changes of different wind turbines

      方案总发电量变化趋势拟合平均尾流损失变化趋势拟合
      WTG1-P模型Y=0.78X+0.23Y=1.45X-0.47
      WTG1-B模型Y=0.81X+0.20Y=1.43X-0.41
      WTG1-F模型Y=0.80X+0.21Y=1.71X-0.70
      WTG2-P模型Y=0.77X+0.25Y=1.52X-0.55
      WTG2-B模型Y=0.83X+0.17Y=1.19X-0.13
      WTG2-F模型Y=0.81X+0.20Y=1.67X-0.69
      WTG3-P模型Y=0.81X+0.20Y=1.46X-0.48
      WTG3-B模型Y=0.83X+0.18Y=1.29X-0.30
      WTG3-F模型Y=0.86X+0.15Y=1.85X-0.86
    • 值得注意的是,表2中所示平均尾流损失拟合关系中的a值存在明显差异,F模型、P模型、B模型对于3种机型的试验平均值分别为1.477、1.303和1.743;表现为F模型最大,P模型次之,B模型最小。

      进一步进行逐机位的尾流分析,以WTG1机型为例,对不同规划容量情景下逐机位的尾流损失分布进行统计,并用箱形图表示如图4所示。可以看到,表示全体机位尾流从大到小排列前25%分位数的箱体上沿、表示后25%分位数的箱体下沿,以及表示中位数的箱体内点状标记等一系列比平均值更具稳定性的统计特征值均随着规划容量增加而出现上升趋势,印证了3.1节中相同场址内机组数目增多而导致更为严重尾流影响的分析结论。另外,表示全体机位尾流中99.7%样本分布区间的箱体外上、下两条短线之间长度随着规划容量增加而变长,说明最大、最小单机尾流之间的差异在扩大,全体机位尾流分布的偏态进一步加剧,出现了长尾效应。原因在于阵列中位于上风向和场址边缘的少数机位可以一直维持着较高的发电效率(尾流损失低),但场址内部和下风向的大部分机位受尾流影响出现较低的发电效率(尾流损失高);并且随着装机总数增加,这部分高尾流损失机位数目增多,最终导致了全体机位尾流分布的不平衡加剧。另一方面,可以看到上述统计特征值的变幅在不同尾流模型中差异明显,如P模型和F模型所形成的尾流分布偏度更大,F模型中高尾流影响占比更大等,原因在于不同尾流模型对单台机组尾流区以及多机组尾流相互影响的描述存在差异。

      图  4  不同规划容量情景下的尾流分布变化

      Figure 4.  Wake distribution changes in different planned capacity situations

      除了导致机组发电效率下降,尾流还会引发湍流强度以及机组疲劳载荷的增加,从而影响机组的安全稳定运行,为此需要在规划容量设置时考虑尾流损失的上限。《风电场微观选址技术规范》[21]中建议平均尾流损失<0.08,在本文中将全场平均尾流损失上限Wmean设为0.08;将2倍Wmean作为逐机位最大尾流损失上限Wmax。若考虑机组安全性约束,扩容引起的尾流损失增长不宜突破WmeanWmax。由图4可知,不同尾流模型的试验结果均显示,本场址在基准容量之上可以适当扩容,但具体的扩容区间增幅受到WmeanWmax的约束。WTG2、WTG3机型也显示出相似的分析结果,图略。进一步对比3种不同容量机型的潜在扩容区间,如表3所示,以Wmean上限来看,WTG3机型的扩容区间比WTG1、WTG2机型多100 MW;以Wmax上限来看,WTG3机型的扩容区间比WTG1、WTG2机型多100~200 MW。可以发现,随着机组单机容量增大,规划容量增幅出现小幅上升的倾向,相关形成机理已在3.1节进行了分析。

      表 3  尾流损失约束下的扩容区间对比

      Table 3.  Comparison of expansion range under wake loss constraint MW

      方案Wmean≤0.08的容量增幅Wmax≤0.16的容量增幅
      WTG1-P模型100500
      WTG1-B模型100600
      WTG1-F模型200500
      WTG2-P模型100400
      WTG2-B模型100500
      WTG2-F模型200400
      WTG3-P模型200600
      WTG3-B模型200700
      WTG3-F模型400700

      需要说明的是,由于国内关于大型海上风电场的研究尚在起步阶段,不同尾流模型在大型海上风电场的应用缺少验证,尚未有确切的评估结论,因此建议根据场址的风资源和水文气象条件,选择适合的尾流模型;或者采用多种尾流模型进行综合比较,避免应用单一模型所可能带来的扩容区间评估偏差。

    • 随着装机数目和规划容量的增加,大型海上风电场工程的投资规模也发生变化,随之而来的投入产出比可能呈现与发电效益不同的变化趋势,为此需要分析不同规划容量情景下的边际效应参数。

      式(13)所定义的边际效应参数E,实质是简化的投入产出比,即假定上网电价和单位千瓦投资均保持恒定,场址扩容带来的发电收益增量与建设规模扩大的投资增量之比,并且为了方便不同机型之间对比,进行了归一化处理。3种机型在不同规划容量情景下的边际效应参数E变化趋势如图5所示。可以看到,在不同尾流模型下,随着规划容量的增加,E均出现下降趋势,其根本原因在于3.1节所分析的尾流损失导致发电量增量减少,从而导致边际效应参数中发电收益增幅不及工程投资增幅。但尾流模型的差异也影响了边际效应参数变化曲线的具体形态。

      图  5  不同规划容量情景下的边际效应参数变化

      Figure 5.  Change of marginal utility parameters in different planned capacity situations

      对比3种不同容量机型可以发现,WTG3机型的边际效应要显著优于其他机型,相同规划容量情景下,WTG3的边际效应参数E要比WTG1、WTG2机型平均超出0.063~0.081,说明更大容量机型具有投入产出比评估上的潜在优势。因此,在3.2节的潜在扩容区间中进一步引入边际效应判据,当E>1,则认为规划容量扩容能够给原有工程带来高于某一预期的投入产出比,具备一定的工程经济性;反之,则认为扩容无效。考虑机组安全性和工程经济性双重约束下的扩容区间称为有效容量增幅,不同尾流模型试验结果的平均值显示:WTG1~WTG3机型取得的有效容量区间分别为200 MW、300 MW和700 MW,有效扩容区间随着机组单机容量增加而增加。

    • 结合3.1~3.3节的分析可知,本文所设置的试验结果显示,在满足现有海上风电场外缘边线包络海域面积要求的基础上,考虑发电效率、机组安全性与工程经济性等多重约束,采用单机容量在10 MW以上机型进行开发时,单个场址的最佳规划容量可以略高于现有基准值;且机型的单机容量越大,扩容区间出现同步增加的趋势,对响应自然资源主管部门的最大限度集约节约用海要求亦有助益。值得注意的是,本文仅限于单个场址情形,未考虑千万千瓦基地内各个场址之间的相互影响,发电收益与投资仅简单地假定为随容量线性增加,与实际条件尚有差异。

      大型海上风电场址规划容量分析与扩容区间的精确评估,面临着诸多挑战。目前最为突出的是大型海上风电场的尾流评估方法与技术仍有较大不确定性,对尾流损失的高估或者低估都将显著影响发电量计算以及连带的工程投资收益测算,给规划容量的准确设置带来干扰。另一方面,应用更大单机容量机型以及装机容量的提升,有可能引起支撑结构、集电海缆、运输吊装等方面设计方案的调整甚至变更,由此带来初期投资或后期运维费用的非线性增加也可能极大压缩有效扩容区间。

      在下一步的研究中,应发展相应的技术框架,建立机组排布、尾流与发电量计算、集电线路拓扑设计、平准化度电成本计算等各个分析环节的数据与工具之间联系,把单个场址的容量设置纳入十吉瓦基地的区域规划与场址细分工作中。充分利用海上风电机组大型化的技术红利,挖掘规划场址存量资源,通过优化提升场址规划装机容量,协调海上风电发展与集约节约用海要求,更高质量地助力“双碳”目标实现。

    • 本文以某个1 GW典型场址为研究对象,利用单机容量在10 MW以上的3种机型,结合风资源图谱与多个海上风电场尾流模型,进行了同场址规划容量从1 GW逐步扩容至2 GW的数值试验,并分析了发电效益与边际效应,取得如下结论:

      1)总发电量和平均尾流损失均随着规划容量的增加而增加,但具体增幅差异显著。原因在于机组数目增加所带来的风能捕获增量被同时产生的更显著的尾流损失部分抵消;在大型海上风电场容量设置中采用更大容量机型,相同规划容量情景下的装机数目更少,排布方案中的机位间距更大,更有利于尾流损失的恢复与控制,具有发电效率上的天然优势。

      2)在满足现有海上风电场外缘边线包络海域面积要求的基础上,考虑发电效率、机组安全性与工程经济性等多重约束,采用单机容量在10 MW以上机型进行开发时,单个场址的最佳规划容量可以略高于现有基准值;且机型的单机容量越大,扩容区间出现同步增加的趋势,更大容量机型具有投入产出比评估上的潜在优势。

      3)不同尾流模型对单台机组尾流区以及多机组尾流相互影响的描述存在差异,尾流模型选择可能会影响容量设置的过程与最终结果,应采用多种尾流模型进行综合比较,避免应用单一模型所可能带来的扩容空间评估偏差。