Research on Risk Assessment System of Pumped Storage Power Station Using Grey Relational TOPSIS Method

More Information
  • Received Date: December 16, 2019
  • Revised Date: March 04, 2020
  •   Introduction  In order to reduce or circumvent various risks in the construction and operation of pumped storage power station projects, this paper aims to establishe a risk assessment system for them.
      Method  Firstly, we established the SWOT-PEST risk analysis matrix by analyzing the development environment, then the risk factors were identified. Secondly, we established the risk evaluation model by using grey correlation analysis and TOPSIS method.
      Result  The results we obtained demonstrate the validity of the model and several rationalization suggestions are put forward.
      Conclusion  This work provides some guidance on risk assessment of similar pumped storage power station projects and further study on risk assessment model.
  • WANG Bingqian,DONG Jianmin,GUAN Qianfeng,et al.Research on Risk Assessment System of Pumped Storage Power Station Using Grey Relational TOPSIS Method[J].Southern Energy Construction,2020,07(增刊2):56-61.

  • [1]
    林铭山. 抽水蓄能发展与技术应用综述 [J]. 水电与抽水蓄能, 2018, 4(1): 1-4+22.

    LINM S.Survey on development and technology application of pumped storage [J]. Hydropower and Pumped Storage, 2018, 4(1): 1-4+22.
    [2]
    郝璐. 山东沂蒙抽水蓄能电站建设项目的风险评价研究 [D]. 保定: 华北电力大学, 2015.

    HAOL. Study on the risk evaluation of construction project of Shandong Yimeng pumped-storage power station [D]. Baoding: North China Electric Power University, 2015.
    [3]
    王大鹏. 国家电网5座抽水蓄能电站同时开工 [N]. 国家电网报, 2019-01-09.

    WANGD P. Five pumped storage power stations of State Grid started operation at the same time [N]. State Grid News, 2019-01-09.
    [4]
    吴强, 孔庆捷. 基于代理型CM模式的抽水蓄能电站工程造价管理研究 [J]. 南方能源建设, 2015, 2(1): 104-109.

    WUQ, KONGQ J. Research on the engineering cost management of pumped-storage power station project with agency CM mode [J].Southern Energy Construction,2015,2(1): 104-109.
    [5]
    聂金峰. 抽水蓄能电站与火电厂联合优化运行分析 [J]. 南方能源建设, 2018, 5(3):61-66.

    NIEJ F. Analysis of combined optimal operation of pumped storage power plants and thermal power plants [J]. Southern Energy Construction, 2018, 5(3):61-66.
    [6]
    张富强, 刘昌, 姜阶华, 等. 适应电力体制改革的抽水蓄能电站价格机制研究 [J]. 水力发电, 2018, 44(4):100-104.

    ZHANGF Q, LIUC, JIANGJ H, et al. Study on pricing mechanism of pumped hydro energy storage (PHES) under China’s electricity tariff reform [J]. Water Power, 2018, 44(4):100-104.
    [7]
    肖达强, 黎舒婷, 舒康安, 等. 我国抽水蓄能电站的管理体制和运营模式探讨 [J]. 电器与能效管理技术, 2016(14):79-84.

    XIAOD Q, LIS T, SHUK A, et al. Research on the management systems and operation patterns of pumped-storage power stations in China [J]. Electrical Energy Management Technology, 2016(14):79-84.
    [8]
    高瑾瑾, 郑源, 李涧鸣. 抽水蓄能电站技术经济效益指标体系综合评价研究 [J]. 水利水电技术, 2018, 49(7):52-158.

    GAOJ J, ZHENGY, LIJ M. Study on comprehensive evaluation of tech-economic benefit index system of pumped storage hydropower station [J]. Water Resources and Hydropower Engineering, 2018, 49(7):52-158.
    [9]
    王诗玉, 吕呈新, 肖宇轩. 基于模糊判别准则的抽水蓄能电站工期风险研究 [J]. 水电与新能源, 2017(7):36-39.

    WANGS Y, LVC X, XIAOY X. Risk analysis for the construction duration of pumped storage power station based on the fuzzy discrimination criterion [J]. Hydropower and New Energy, 2017(7):36-39.
    [10]
    于心怡. 基于综合风险评价的光伏发电项目投资决策模型研究 [D]. 保定:华北电力大学, 2014.

    YUX Y. Research on investment decision model of Photovoltaic power generation project based on integrated risk assessment [D]. Baoding: North China Electric Power University, 2014.
  • Cited by

    Periodical cited type(6)

    1. 余恩海,佟佳颖,刘琳. 基于组合赋权–云模型的抽蓄电站高质量发展评价体系. 电力科学与工程. 2024(05): 64-71 .
    2. 边伟,王明莹. 电力市场抽水蓄能与新能源联合运营的协同优化研究. 建筑经济. 2024(S1): 424-427 .
    3. Le Liu,Xueyu Chen,Dexin Li,Chang Liu,Dunnan Liu,Genzhu Li. Evaluation method for assessing the auxiliary service transaction mechanism in regional power markets. Global Energy Interconnection. 2023(02): 238-252 .
    4. 马萧萧,朱安平,余蔚青,刘新,李璇. 抽水蓄能电站建设期水土流失及其次生灾害风险评价. 水土保持通报. 2022(02): 157-165 .
    5. 余顺坤,宋宇晴. 基于变分自编码器-物元分析法的抽水蓄能电站效能综合评价. 现代电力. 2022(03): 295-301 .
    6. 李波,刘鑫屏. 基于最优权重融合的火电机组智能燃烧优化方案评价. 南方能源建设. 2022(03): 94-101 . 本站查看

    Other cited types(5)

Catalog

    Qian HAN

    1. On this Site
    2. On Google Scholar
    3. On PubMed

    Tables(9)

    Article Metrics

    Article views (700) PDF downloads (40) Cited by(11)

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return