Kai WANG. Discussion on the Development and Construction Management for Wind Farms in Mountainous Area[J]. SOUTHERN ENERGY CONSTRUCTION, 2018, 5(2): 67-70. DOI: 10.16516/j.gedi.issn2095-8676.2018.02.009
Citation: Kai WANG. Discussion on the Development and Construction Management for Wind Farms in Mountainous Area[J]. SOUTHERN ENERGY CONSTRUCTION, 2018, 5(2): 67-70. DOI: 10.16516/j.gedi.issn2095-8676.2018.02.009

Discussion on the Development and Construction Management for Wind Farms in Mountainous Area

More Information
  • Received Date: May 09, 2018
  • Revised Date: May 15, 2018
  •   [Introduction]  The development and construction management of the montanic wind power differs significantly from the management of the traditional thermal power projects, this requires a wind power adapted constructing mode, which can reduce the risks during the wind power project and lubricate its construction process.
      [Method]  This discussion pointed out the difficulties and the key points in the construcion of montanic wind power, and discussed its development and management works.
      [Result]  The results indicate that the refined management measures direct to the montanic wind power construction are necessary. The measures include the staged objectives such as anemometry, the wind resource evaluation, the selection of wind turbine, micro-sitting selection and road design. Besides, the management of the building process, including QS, safety standards, duration of the project and daily communication, is also of the essence for the montanic wind power project.
      [Conclusion]  The results contribute to the wind power plants that build and operate in mountainous areas, and may be insrtuctive to the healthy development of wind power in China.
  • [1]
    刘永前. 风力发电厂 [M]. 北京:机械工业出版社,2013.
    [2]
    董林,陈江巍. 浅谈山区风电场建设进度管理实践[J]. 水电与新能源,2016(3):74-75.
    [3]
    中华人民共和国国家发展和改革委员会. 可再生能源发展“十三五”规划 [R]. 北京:中华人民共和国国家发展和改革委员会,2016.
    [4]
    杨竞锐,戴谦训,周毅. 高原山地风电场风资源利用研究[J]. 云南电力技术,2014,42(4):9-19.

    YANG J R,DAI Q X,ZHOU Y. Reasearch on effective utilization of plateau mountainous wind power[J]. Yunnan Electric Power,2014,42(4):9-19.
    [5]
    张怀全. 风资源与微观选址:理论基础与工程应用 [M]. 北京:机械工业出版社,2013.
    [6]
    王洋,周向阳. 基于Scada数据的风电场改扩建数值模拟研究[J]. 南方能源建设,2017,4(3):92-96.

    WANG Y,ZHOU X Y. Reasearch on the method for the reconsteuction and expansion of the wind farm based on the Scada data[J]. Southern Energy Construction,2017,4(3):92-96.
    [7]
    张伟波,娄样,王承才. 大力推动风电开发系统化管理[J]. 中国电力企业管理,2015(15):64-65.
    [8]
    纪志国. 风电场建设进度管理研究[J]. 能源与节能,2013(7):37-38+43.
  • Related Articles

    [1]WEI Xin, ZHANG Zongyi, YANG Liming. Key Issues of China's Carbon Pricing Mechanism Construction[J]. SOUTHERN ENERGY CONSTRUCTION, 2024, 11(5): 57-62. DOI: 10.16516/j.ceec.2024.5.06
    [2]LIU Huaquan, LI Yuansong, PAN Shengping, ZHANG Xin, ZHAO Yong. Key Technology of Construction Process Control of Guide Frame Platform Suction Bucket Foundation[J]. SOUTHERN ENERGY CONSTRUCTION, 2023, 10(1): 98-104. DOI: 10.16516/j.gedi.issn2095-8676.2023.01.012
    [3]Tian XIONG, Xingye LIU. Discussion on Key Points in Electrical Design of Typical Underground Municipal Engineering[J]. SOUTHERN ENERGY CONSTRUCTION, 2022, 9(S1): 92-98. DOI: 10.16516/j.gedi.issn2095-8676.2022.S1.014
    [4]Jinchao LIU. Research on Key Technologies of Pile Driving Construction for Monopile[J]. SOUTHERN ENERGY CONSTRUCTION, 2022, 9(1): 47-51. DOI: 10.16516/j.gedi.issn2095-8676.2022.01.007
    [5]Jinjian Zheng. Key Points of Energy Saving Report Compilation for New H-class Gas Turbine Project Under Carbon Neutralization Target[J]. SOUTHERN ENERGY CONSTRUCTION, 2021, 8(2): 25-30. DOI: 10.16516/j.gedi.issn2095-8676.2021.02.004
    [6]Discuss on Key Problems of Energy Development Strategy in China[J]. SOUTHERN ENERGY CONSTRUCTION, 2019, 6(1): 22-23. DOI: 10.16516/j.gedi.issn2095-8676.2019.01.004
    [7]REN Wei. Optimization Analysis and Discussion on Fan Sector Management in Mountain Wind Farm[J]. SOUTHERN ENERGY CONSTRUCTION, 2018, 5(S1): 255-261. DOI: 10.16516/j.gedi.issn2095-8676.2018.S1.047
    [8]YUAN Guokai, ZHU Guangtao, HUANG Zhijun. Construction and Installation Risk Management of Offshore Wind Farm[J]. SOUTHERN ENERGY CONSTRUCTION, 2016, 3(S1): 190-193. DOI: 10.16516/j.gedi.issn2095-8676.2016.S1.043
    [9]Siwei LIANG. Discuss on Key Points of Energy Saving Evaluation for Thermal Power Projects[J]. SOUTHERN ENERGY CONSTRUCTION, 2016, 3(4): 26-31. DOI: 10.16516/j.gedi.issn2095-8676.2016.04.006
    [10]Chuangang GUO. Study on Construction Management of Overseas Thermal Power EPC Project[J]. SOUTHERN ENERGY CONSTRUCTION, 2016, 3(1): 54-57. DOI: 10.16516/j.gedi.issn2095-8676.2016.01.012
  • Cited by

    Periodical cited type(5)

    1. 丁爱军,樊勇,易生,张凤. “协同+清单化”风电工程建设管理机制的研究与应用. 水电站机电技术. 2024(06): 116-117+144 .
    2. 邓家裕. 风电项目建设中加强工程勘察设计的管理. 水电与新能源. 2022(07): 53-56 .
    3. 申新贺,陈广宇,姜婷婷,朱金奎. 考虑冰冻气候的山地风电场发电量精细化研究. 可再生能源. 2021(06): 778-783 .
    4. 王冀檬. 高山风电项目安全管理与风险分析. 机电信息. 2020(08): 110-111 .
    5. 张韬. 浅谈风电项目建设过程中如何加强安全管理. 居舍. 2019(19): 130 .

    Other cited types(1)

Catalog

    Kai WANG

    1. On this Site
    2. On Google Scholar
    3. On PubMed

    Article Metrics

    Article views (789) PDF downloads (43) Cited by(6)

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return