HU Rong, JIAN Xianghao. Analysis on the No.3 Connecting Transformer Incoming Feeder Scheme in Shenzhen Substation[J]. SOUTHERN ENERGY CONSTRUCTION, 2015, 2(S1): 76-79. doi: 10.16516/j.gedi.issn2095-8676.2015.S1.016
Citation: HU Rong, JIAN Xianghao. Analysis on the No.3 Connecting Transformer Incoming Feeder Scheme in Shenzhen Substation[J]. SOUTHERN ENERGY CONSTRUCTION, 2015, 2(S1): 76-79. doi: 10.16516/j.gedi.issn2095-8676.2015.S1.016

Analysis on the No.3 Connecting Transformer Incoming Feeder Scheme in Shenzhen Substation

doi: 10.16516/j.gedi.issn2095-8676.2015.S1.016
  • Received Date: 2015-10-23
  • Shenzhen substation is ultra-scale extending the NO.3 connecting transformer. 500 kV XLPE cable and GIB incoming feeder schemers of the NO.3 connecting transformer were analysed through techno-economic comparison in this paper. Compering to XLPE cable, GIB is more technically mature, superior performance and reliable. On the other side of life cycle cost (LCC), GIB schemer is economically feasible. The NO.3 connecting transformer incoming feeder finally adopt GIB schemer with length of 750 meters, its aerial installation path contains roof, wall, road and narrow area. Engineering experiences are summarized from three aspects of technical parameters, schemer design and foundation constructing. These experiences could be used for reference in other substation extending, where the tension space is too difficult to arrange and GIB is adopted.
  • 通讯作者: 陈斌, bchen63@163.com
    • 1. 

      沈阳化工大学材料科学与工程学院 沈阳 110142

    1. 本站搜索
    2. 百度学术搜索
    3. 万方数据库搜索
    4. CNKI搜索

Article Metrics

Article views(182) PDF downloads(26) Cited by()

Related

Analysis on the No.3 Connecting Transformer Incoming Feeder Scheme in Shenzhen Substation

doi: 10.16516/j.gedi.issn2095-8676.2015.S1.016

Abstract: Shenzhen substation is ultra-scale extending the NO.3 connecting transformer. 500 kV XLPE cable and GIB incoming feeder schemers of the NO.3 connecting transformer were analysed through techno-economic comparison in this paper. Compering to XLPE cable, GIB is more technically mature, superior performance and reliable. On the other side of life cycle cost (LCC), GIB schemer is economically feasible. The NO.3 connecting transformer incoming feeder finally adopt GIB schemer with length of 750 meters, its aerial installation path contains roof, wall, road and narrow area. Engineering experiences are summarized from three aspects of technical parameters, schemer design and foundation constructing. These experiences could be used for reference in other substation extending, where the tension space is too difficult to arrange and GIB is adopted.

HU Rong, JIAN Xianghao. Analysis on the No.3 Connecting Transformer Incoming Feeder Scheme in Shenzhen Substation[J]. SOUTHERN ENERGY CONSTRUCTION, 2015, 2(S1): 76-79. doi: 10.16516/j.gedi.issn2095-8676.2015.S1.016
Citation: HU Rong, JIAN Xianghao. Analysis on the No.3 Connecting Transformer Incoming Feeder Scheme in Shenzhen Substation[J]. SOUTHERN ENERGY CONSTRUCTION, 2015, 2(S1): 76-79. doi: 10.16516/j.gedi.issn2095-8676.2015.S1.016

Catalog

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return