LI Peng, HE Xiyang, HUANG Zhanghua. Settlement Calculation of Turbine and Generator Foundation[J]. SOUTHERN ENERGY CONSTRUCTION, 2015, 2(S1): 119-122. doi: 10.16516/j.gedi.issn2095-8676.2015.S1.026
Citation: LI Peng, HE Xiyang, HUANG Zhanghua. Settlement Calculation of Turbine and Generator Foundation[J]. SOUTHERN ENERGY CONSTRUCTION, 2015, 2(S1): 119-122. doi: 10.16516/j.gedi.issn2095-8676.2015.S1.026

Settlement Calculation of Turbine and Generator Foundation

doi: 10.16516/j.gedi.issn2095-8676.2015.S1.026
  • Received Date: 2015-11-11
  • turbo generator is the heart of the power plant, and is a precision instrument for high speed operation. In order to ensure the normal operation of the turbo generator, as the foundation of its supporting structure, the design requirement (especially settlement control) is very high. The settlement calculation method provided by the foundation design specification is applicable to the independent foundation, and the calculation result is a settlement of a point, which is not suitable for the turbine generator foundation. There are three parts in this paper. First, through appropriate assumption, the settlement calculation method based on the independent foundation is extended to other arbitrary foundation forms. Second, based on the actual engineering practice example, the design method based on the above assumptions is shown; third, the author tries to simplify the design process, and to establish a more general standard for the eccentric design of dynamic machine and other building and structure, which is sensitive to uneven settlement.
  • 通讯作者: 陈斌, bchen63@163.com
    • 1. 

      沈阳化工大学材料科学与工程学院 沈阳 110142

    1. 本站搜索
    2. 百度学术搜索
    3. 万方数据库搜索
    4. CNKI搜索

Article Metrics

Article views(210) PDF downloads(25) Cited by()

Related

Settlement Calculation of Turbine and Generator Foundation

doi: 10.16516/j.gedi.issn2095-8676.2015.S1.026

Abstract: turbo generator is the heart of the power plant, and is a precision instrument for high speed operation. In order to ensure the normal operation of the turbo generator, as the foundation of its supporting structure, the design requirement (especially settlement control) is very high. The settlement calculation method provided by the foundation design specification is applicable to the independent foundation, and the calculation result is a settlement of a point, which is not suitable for the turbine generator foundation. There are three parts in this paper. First, through appropriate assumption, the settlement calculation method based on the independent foundation is extended to other arbitrary foundation forms. Second, based on the actual engineering practice example, the design method based on the above assumptions is shown; third, the author tries to simplify the design process, and to establish a more general standard for the eccentric design of dynamic machine and other building and structure, which is sensitive to uneven settlement.

LI Peng, HE Xiyang, HUANG Zhanghua. Settlement Calculation of Turbine and Generator Foundation[J]. SOUTHERN ENERGY CONSTRUCTION, 2015, 2(S1): 119-122. doi: 10.16516/j.gedi.issn2095-8676.2015.S1.026
Citation: LI Peng, HE Xiyang, HUANG Zhanghua. Settlement Calculation of Turbine and Generator Foundation[J]. SOUTHERN ENERGY CONSTRUCTION, 2015, 2(S1): 119-122. doi: 10.16516/j.gedi.issn2095-8676.2015.S1.026